I took today (Friday) off, mostly because Axel was coming over and we had several things to cover. Besides, the weather forecast was sunny and who needs work anyway? Except that, without the pay that work brings in, barns can't be remodeled!
The first order of business was getting the staircases ordered. Mr. Voit came over and we went through all the various options and choices. The entrance stairs will run in a simple "L-shape" with the long part on the back wall. That wall will be mostly bare stone and we think the steamed birch stairs will look nice against the sandstone. ("Steamed birch" is another of those terms that we have had to learn. ) The stairs up to the sleeping loft will be even simpler, with pine sides and oak treads.
The rest of the meeting with Axel covered every other contractor. I'll try to summarize, in the order things need to be done:
- Plumber: Axel and our neighborhood plumber, Mr. Gumbrecht, are not communicating. This is a serious problem because the next step has to be placing the sewer lines and the water lines in the floor of the entrance/bath. Pouring the floor is a requirement before the stairs and the bathroom walls can be done. Best hope for when: sewer line next week, floor the week after.
- Back door and shutters: Mr. Löhr has given us OK bids for the back door and the shutters over the front window. However, actually building the door depends once again on the height of the entrance floor. The shutters can be done anytime, but we are still trying to get a design that is both functional and fitting to the style of our old/new barn. Axel has some ideas and he said he'd send a sketch.
- Plaster (outside): Mr. Fritsch, another Pommersfelden local, has completed a bid for cleaning the walls outside and patching here and there. The idea is that the front side will be re-plastered, but the sides will only get new plaster where there is new cement or where we want a small amount of insulation. The old sand stone will get some sort of coating to help it not wash away. I will try to do the removal of old plaster myself. Swinging a hammer at old stuff seems within my skill level. All this should happen in August and September.
- Insulation and walls: We need to install the ceiling insulation and the lath that will hold the drywall before our electrician can do his thing. Slavco, our prime miscellaneous contractor, is pretty booked but we will work to get him on Fridays and weekends, starting in a couple weeks. Here too, I'll contribute some "sweat-equity". Later, in September or October, Slavco and his team will do the heavier lifting associated with drywall and installing the insulation and covering of the garage ceiling.
- Tiles: We didn't talk about tiling for the bathroom and the entrance floor. I'll remind Axel that, as a minimum, we need to get a slot in Mr.
- Electrical: Mr. Kramer has submitted a bid that fits with our latest plans for lights and power outlets. It's more than earlier estimates, but directly connected with the details we've added to our plan. In any event, he won't work until some of Slavco's work is done: maybe end of August? Later, after drywall, the balance of the electrical installation should happen.
- Lights: With Mr. Kramer's schedule, it seems we won't be needing the lights from Nysets' until September, at the earliest. That's OK, since we need to pace our spending, at least a little. Showing our good planning, the long summer days will be ending about then as well.
- Paint, flooring, etc: These are more tasks for do-it-yourself. It's looking like October or November.
- Furniture: Finally, there is the question of furniture. Mostly this means getting our stored-for-10-years things from San Jose. This sounds like a good Christmas present!
|